Tyson Park Redevelopment
Tyson Park updates are coming soon! After securing funding and navigating land use requirements, park improvements will begin in 2026. Watch the recording of the December virtual neighborhood meeting to see the proposed final park design and updated project timeline.
Proposed Park Design
In 2024, Willamalane collected community input on park features for future upgrades to Tyson Park. Feedback from meetings, focus groups, and hundreds of survey responses shaped the final park design. Later, while navigating land use requirements, emergency access ways were incorporated. Watch the recording of the December virtual neighborhood meeting for a full overview of the upcoming changes and project timeline.
Tyson Park Development Documents
| TysonParkFinalDesign | 1.37 MB |
Project Timeline
- Feb.-March 2024: Community members provided input on future updates to Tyson Park through surveys, meetings, and focus groups.
- April 2024-Sept. 2025: Willamalane sought additional funding and worked with the City of Springfield on land use review and updated permitting requirements. New emergency access routes were added to the design, extending the original project timeline.
- Fall 2025-Winter 2026: The project is in the permitting process.
- December 16, 2025: A virtual neighborhood meeting showed the updated project timeline and proposed final park design.
- Spring/Summer 2026: Construction will take place at Tyson Park.
- Fall 2026: Estimated completion for Tyson Park redevelopment work.
The project timeline may shift as needed.